Due to the effects of the earthquake, adjustments will be made to production operations of plants for completed vehicles in Japan as follows.
We sincerely apologize for the inconvenience caused to our suppliers and people in those regions, due to these changes.
Production suspension for 14 production lines at nine plants (Among a total of 28 lines at 15 plants)
Plant | Period of production suspension (February) | Production Vehicle | |
---|---|---|---|
Toyota Motor CorporationTakaoka Plant | Production line #2 | 18 (Thu), 19 (Fri), 20 (Sat) | Harrier, Prius α, RAV4 |
Toyota Motor CorporationTahara Plant | Production line #1 | Prado, GX, 4Runner | |
Production line #3 | 17 (Wed), 18 (Thu), 19 (Fri), 20 (Sat) | LS, IS, RC, NX | |
Toyota Motor Kyushu Co., Ltd.Miyata Plant | Production line #1 | 19 (Fri) 2nd shift, 20 (Sat) | NX, UX, CT |
Production line #2 | 20 (Sat) | ES, RX | |
Toyota Motor East Japan, Inc. (TMEJ)Iwate Plant | Production line #1 | 18 (Thu) 2nd shift, 19 (Fri), 20 (Sat) | C-HR, Aqua |
Toyota Auto Body Co., Ltd.Fujimatsu Plant | Production line #1 | 17 (Wed) 2nd shift, 18 (Thu), 19 (Fri), 20 (Sat) | LC70 |
Toyota Auto Body Co., Ltd.Yoshiwara Plant | Production line #1 | LC200/LX | |
Production line #2 | LC70 | ||
Gifu Auto Body Co., Ltd. | Production line #2 | 18 (Thu), 19 (Fri), 20 (Sat) | Coaster |
Toyota Industries Corporation | Production line #301 | 17 (Wed), 18 (Thu), 19 (Fri), 20 (Sat) | RAV4 |
Production line #302 | |||
Hino Motors, Ltd.Hamura Plant | Production line #1 | 18 (Thu), 19 (Fri), 20 (Sat) | Land Cruiser Prado, FJ Cruiser |
Production line #2 | Dyna |
Notes
- Line #2 at Gifu Auto Body operates at one shift.
- 1st shift only for February 20 (Sat).